Installation Guide

How to Replace an Old Round Cooling Tower Without Modifying Existing Piping or Foundation

COOLTEK 2026-04-27 Approx. 10 min read

For factories that need to replace aging cooling towers, the biggest concern is usually not the cost of the new equipment itself, but the downtime and civil engineering work required during replacement. Modifying piping, reconstructing foundations, and extended shutdowns can all bring significant production losses and additional costs.

The COOLTEK LH series is specifically designed to address this pain point. Starting from the physical dimensions of standard old round towers, this article explains the five-step in-place replacement method and the specific conditions under which it applies.

LH series cooling tower in-place replacement of old round tower without modifying piping

The COOLTEK LH series is designed to be physically compatible with standard old round towers, enabling direct in-place replacement without modifying piping or foundations.

1. Why Can the LH Series Be Replaced In Place?

1.1 Physical Compatibility Design

The core design principle of the COOLTEK LH series is physical compatibility with standard old round towers. Specifically:

  • Anchor bolt pitch circle diameter (P.C.D.): The LH series P.C.D. is designed to match the standard dimensions of old round towers, so existing foundation anchor bolts can be reused directly.
  • Inlet and outlet flange positions: The LH series inlet and outlet flange heights and positions are compatible with standard old round tower connections, eliminating the need to modify water supply and return piping.
  • Overflow and drain port positions: These are also designed to match standard positions, so existing drainage piping can be reused.

This compatibility design means that in most cases, the new tower can be installed directly in the footprint of the old tower without any civil engineering work.

1.2 Scope of Application

The in-place replacement method is applicable when the following conditions are met:

  • The old tower is a standard round cooling tower (the most common type in Vietnam's industrial zones).
  • The foundation is in good condition with no structural damage.
  • The existing piping uses standard flange connections.
  • The required cooling capacity of the new tower is within the LH series flow range (8–1,000 m³/h).

If the old tower is a non-standard model or the foundation has significant damage, a site survey should be conducted first to assess whether in-place replacement is feasible.

2. Five-Step In-Place Replacement Method

Step 1: Pre-Replacement Survey and Confirmation

Before replacement, the following information must be confirmed on site:

Survey ItemContent to ConfirmPurpose
Old tower modelBrand, model, flow rateConfirm LH series compatibility
Foundation dimensionsP.C.D., anchor bolt specificationsConfirm whether existing bolts can be reused
Piping connectionsFlange specifications, pipe diameters, heightsConfirm whether piping modifications are needed
Electrical connectionPower supply specifications, cable routingConfirm electrical connection plan
Lifting conditionsAvailable space, crane accessPlan lifting equipment and route

Step 2: Preparation Before Shutdown

To minimize downtime, the following preparations should be completed before the planned shutdown:

  • New tower delivery and on-site inspection to confirm no transport damage.
  • Preparation of all tools and materials: gaskets, bolts, grounding wire, sealant.
  • Coordination of the construction team: crane operator, electrician, pipe fitter.
  • Confirmation of the shutdown window and notification to relevant production departments.

Step 3: Removal of the Old Tower

After shutdown, the old tower is removed in the following sequence:

  1. Drain the basin water and disconnect the electrical connection.
  2. Disconnect the inlet and outlet water pipe flanges.
  3. Remove the anchor bolts (or loosen them if they are to be reused).
  4. Lift out the old tower body using a crane.

The entire removal process usually takes 2–3 hours.

Step 4: Installation of the New Tower

  1. Clean the foundation surface and check levelness (deviation ≤ ±2 mm).
  2. Lower the new LH tower body into position using a crane.
  3. Align the anchor bolt holes and tighten the bolts (torque according to specifications).
  4. Connect the inlet and outlet water pipe flanges, using new rubber gaskets.
  5. Connect the electrical power supply and check motor rotation direction.
  6. Connect the overflow and drain pipes.

Step 5: Commissioning and Handover

After installation, the following commissioning checks must be completed before returning to production:

  • Fill the basin with water and check all connection points for leaks.
  • Start the fan and check operating current (should be within the nameplate range).
  • Check vibration value (should be ≤ 2.8 mm/s for standard industrial equipment).
  • Measure outlet water temperature to confirm it meets design requirements.
  • Record all commissioning data as baseline for future maintenance reference.

The entire replacement process — from shutdown to restart — typically takes 8–12 hours, allowing the factory to complete the replacement within a single shift.

3. Common Questions and Solutions

3.1 What If the Foundation Anchor Bolt Positions Don't Match?

If the old tower is a non-standard model with a P.C.D. that doesn't match the LH series, there are two solutions: use an adapter base plate (COOLTEK can provide custom fabrication), or drill new anchor bolt holes in the existing foundation (requires structural assessment). In most cases, the adapter base plate solution is faster and more economical.

3.2 What If the Pipe Diameters Don't Match?

If the existing piping diameter differs from the LH series flange specifications, reducer flanges can be used for connection. COOLTEK provides standard reducer flanges for common pipe size combinations, which can be installed directly without custom fabrication.

LH series FRP housing salt spray test corrosion resistance

The FRP housing of the LH series passes the ASTM B117 salt spray test, with a service life of more than 15 years in coastal industrial environments.

Reference standards: GB/T 50392-2016 Code for Design of Mechanical Draft Cooling Towers; ASHRAE 2019 HVAC Systems and Equipment, Chapter 40; ASTM B117 salt spray test standard.

Frequently Asked Questions

Can the LH series really replace old round towers without modifying piping?
Yes — the LH series P.C.D. and flange positions are designed to match standard old round towers. In most cases, existing foundation anchor bolts and water supply/return piping can be reused directly. A pre-replacement site survey is recommended to confirm compatibility.
How long does the replacement take?
For a standard in-place replacement, the entire process from shutdown to restart typically takes 8–12 hours. With adequate preparation (tools, materials, and team coordination completed before shutdown), it can be done within a single shift.
What if the old tower is a non-standard model?
If the old tower P.C.D. does not match the LH series standard, an adapter base plate solution can be used. COOLTEK provides custom fabrication. Contact our technical team for a site assessment.
Does the new tower need a new foundation?
No — if the existing foundation is in good structural condition (no cracks, no settlement, levelness within ±2 mm), it can be reused directly. Foundation reconstruction is only required if there is significant structural damage.