Engineering Practice

Induction Furnace Cooling System Selection Guide: Why Induction Coils Require a Closed-Circuit Cooling Tower | COOLTEK

COOLTEK 2026-04-28 About 10 minutes

Figure 1: Dual-circuit structure of an induction furnace coil cooling system — the inner circuit for pure water circulation and the outer circuit for spray-based heat rejection through the AWA closed-circuit tower.

Problem Definition: Selection Constraints for an Induction Furnace Cooling System

The cooling system selection for an induction furnace is governed by three hard constraints:

  • Water quality constraint: The inner diameter of the induction coil copper tube is 8–15 mm. OEMs clearly require cooling water conductivity below 200–300 μS/cm and hardness below 50–100 mg/L as CaCO₃. Under Vietnamese water quality conditions, an open cooling tower cannot meet these requirements.
  • Temperature constraint: Coil inlet water temperature is usually required to be below 35°C, and outlet water temperature below 45°C. In Vietnam, summer wet-bulb temperature is about 28–30°C. The outlet water temperature of an open tower is usually 32–38°C, leaving very little temperature margin.
  • Reliability constraint: An induction furnace is usually the bottleneck equipment in a casting or forging production line. A cooling system failure directly stops the production line, and downtime losses are typically 5–20 million VND per hour.

Physical Principle: Calculating the Heat Load of an Induction Coil

The cooling heat load of an induction coil comes from two sources:

  • Joule heat of the coil itself, or I²R loss: This is usually 5–8% of the rated power of the induction furnace. For a 500 kW induction furnace, coil Joule heat is about 25–40 kW.
  • Furnace radiation heat transfer: The metal charge inside the furnace is at 1000–1600°C and transfers heat to the coil through radiation and convection. This accounts for about 3–5% of rated power, or 15–25 kW.
For a 500 kW induction furnace, the total coil cooling heat load is about 40–65 kW. With a safety factor of 1.2, the design cooling heat load is 78 kW.

How to calculate the required cooling water flow from Joule heat and radiation heat transfer

Assume the inlet-outlet water temperature difference ΔT = 10°C, and the specific heat capacity of cooling water c = 4.18 kJ/(kg·K):

Flow rate Q = P / (c × ΔT × ρ) = 78 / (4.18 × 10 × 1.0) ≈ 1.87 m³/h ≈ 31 L/min

Considering pipeline resistance and uneven distribution, the design flow rate is set at 35 L/min.

Correcting the AWA closed-circuit tower selection heat load for Vietnamese weather conditions

AWA closed-circuit tower selection heat load = coil cooling heat load × system thermal efficiency correction factor (1.1–1.2) = 78 × 1.15 ≈ 90 kW

Under typical Vietnamese meteorological conditions, with a wet-bulb temperature of 28°C, inlet water temperature of 40°C, and outlet water temperature of 32°C, the AWA selection table indicates AWA-30, with a rated heat rejection capacity of 100 kW and an inner-circuit flow rate of 40 m³/h.

COOLTEK Solution: AWA Dual-Circuit Configuration

The standard configuration is: AWA closed-circuit tower for outer-circuit heat rejection + plate heat exchanger for heat exchange between the inner and outer circuits + inner-circuit circulating pump + water softener + corrosion and scale inhibitor dosing unit.

EquipmentSpecificationFunction
AWA closed-circuit towerAWA-30, heat rejection capacity 100 kWOuter-circuit heat rejection; spray water evaporates outside the coil
Plate heat exchangerHeat transfer area 2 m²; heat transfer coefficient 3000 W/(m²·K)Heat transfer between inner and outer circuits; physical isolation
Inner-circuit circulating pumpHead 20 m; flow rate 35 L/minDrives pure water circulation in the inner circuit
Water softenerOutlet hardness <50 mg/LSoftens make-up water for the inner circuit
Dosing unitCorrosion and scale inhibitor; dosage 50–100 mg/LMaintains stable inner-circuit water quality
Note: Some AWA models, such as the AWA-Y series, integrate the circulating pump, water softener, and dosing unit into one packaged unit, so these devices do not need to be configured separately.

Standards Verification: Cooling Water Quality Requirements of Mainstream Induction Furnace OEMs

ParameterOEM Requirement (Combined)Actual Value from Open Tower (Vietnam)Actual Value in AWA Inner Circuit
Conductivity<200–300 μS/cm800–2000 μS/cm150–220 μS/cm ✓
Total hardness (CaCO₃)<50–100 mg/L400–800 mg/L<50 mg/L ✓
pH7.0–8.56.5–8.0, with large fluctuations7.5–8.0 ✓
Chloride ion<50 mg/L50–150 mg/L<20 mg/L ✓

Extended Questions

  • If several induction coils are cooled in parallel, how should the total heat load and flow distribution be calculated when selecting an AWA tower?
  • In northern Vietnam during winter, when air temperature is 5–10°C, will the AWA closed-circuit tower provide excessive cooling? How can the outlet water temperature be controlled so it does not fall below the OEM minimum requirement?
  • How should the head of the inner-circuit circulating pump be calculated? How can the pressure drop of the induction coil copper tube be estimated?
Recommended next reading: AWA Heat Rejection Principle: Spray Water Evaporates Outside the Coil While Process Water Circulates in a Sealed Coil

Frequently Asked Questions

Why should an induction furnace cooling system not use an open cooling tower?
Under typical Vietnamese water conditions, when the concentration cycle of an open tower reaches 3, conductivity rises to 800–2000 μS/cm and total hardness rises to 400–800 mg/L. These values exceed the <200–300 μS/cm and <50–100 mg/L requirements commonly specified by induction furnace OEMs. Excess minerals precipitate as scale on the inner wall of the induction coil copper tube, whose inner diameter is 8–15 mm, causing the coil to overheat and burn out.
What size AWA closed-circuit tower is required for a 500 kW induction furnace?
The coil cooling heat load of a 500 kW induction furnace is about 40–65 kW. After applying a 1.2 safety factor and correcting for system thermal efficiency, the AWA selection heat load is about 90 kW. Under typical Vietnamese weather conditions, with a wet-bulb temperature of 28°C, the AWA-30 model with a rated heat rejection capacity of 100 kW can meet the requirement.
What auxiliary equipment is required for the inner circuit of an AWA closed-circuit tower?
The standard configuration includes a plate heat exchanger for heat transfer between the inner and outer circuits, an inner-circuit circulating pump with a 20 m head and 35 L/min flow rate, a water softener with outlet hardness <50 mg/L, and a corrosion and scale inhibitor dosing unit. The AWA-Y integrated unit already incorporates these devices, so separate configuration is not required.